June 8, 2006 Initiation of President's dumping and subsidy investigation.
June 9, 2006 Initial compilation of CBSA exhibits available
June 23, 2006 Statement of Reasons Re: Initiation of Investigation
June 29, 2006 Importers' responses to CBSA's Request for Information due (applicable to each importer that is not associated with the exporter of the goods)
July 20, 2006 Importers' responses to CBSA's Request for Information due (applicable to each importer that is associated with the exporter of the goods)
July 31, 2006 Chinese Government response to CBSA's Request for Information due
July 31, 2006 Exporters' responses to CBSA's Request for Information due
October 20, 2006 Preliminary Determination and/or Termination of President's dumping and/or subsidy investigation
November 3, 2006 Statement of Reasons (Preliminary Determination and/or Termination) issued.
In the event of a Preliminary Determination
October 20, 2006 Exporter and Importer ruling letters available
November 3, 2006 Revised import statistics available.
November 20, 2006 Closing of the Record Date
November 27, 2006 Case Arguments due from all parties
December 4, 2006 Reply submissions due from all parties in respect of case arguments
December 15, 2006 Case Arguments due from all parties concerning exhibits posted on December 8 or December 13, 2006 only.
December 20, 2006 Reply submissions due from all parties in respect of case arguments submitted concerning exhibits posted on December 8 or December 13, 2006 only.
January 18, 2007 Final Determination and/or Termination of President's dumping and/or subsidy investigation
January 18, 2007 Exporter and importer ruling letters available.
February 2, 2007 Statement of Reasons (Final Determination and/or Termination) issued